Chandra Asri delays turnaround at cracker

Chandra Asri delays turnaround at cracker

Jun 11, 2026

Chandra Asri Petrochemical has postponed the shutdown of its cracker in Cilegon. A source in Indonesia informed a team member, “The company has postponed the maintenance turnaround at its cracker to January 2026. The shutdown was originally planned for November 2025 and expected to last around 50 days. However, further details of the current turnaround duration remain unconfirmed, as no official statement has been obtained from an authorized company representative.” Located in Cilegon, Indonesia, the cracker has an ethylene production capacity of 900,000 mt/year and propylene production capacity of 490,000 mt/year.